My PAPER 26-Feb-2013
Time : 11.00 AM

52 Questions Total

4 ques X 2 Marks
4 ques X 3 Marks
4 ques X 5 Marks

- Function Points Components (5)
- Phase of Maintenence Process (5)
- What are types of Risk (2)
- Accurate Effort Estimation (3)
- Let us suppose optimistic, most likely and pessimetic estimates for  system testing are 10,15,20 calculate estimated time using PERT (5)
- One question is Scerios Bases (5)
- How a project manager should handle the Risk (3)

-- Do Good Have Good --